• Skip to primary navigation
  • Skip to main content
Logo

Work Zone Safety Information Clearinghouse

Library of Resources to Improve Roadway Work Zone Safety for All Roadway Users

  • About
  • Join Listserv
  • Contact
  • Twitter
  • Facebook
  • LinkedIn
  • Work Zone Data
    • At a Glance
    • National & State Traffic Data
    • Work Zone Traffic Crash Trends and Statistics
    • Worker Fatalities and Injuries at Road Construction Sites
  • Topics of Interest
    • Commercial Motor Vehicle Safety
    • Smart Work Zones
    • Transportation Management Plans
    • Accommodating Pedestrians
    • Worker Safety and Welfare
    • Project Coordination in Work Zones
  • Training
    • Flagger
    • Online Courses
    • Toolboxes
    • FHWA Safety Grant Products
    • Certification and
      Accreditation
  • Work Zone Devices
  • Laws, Standards & Policies
    • COVID-19 Guidance
  • Public Awareness
  • Events
  • About
  • Listserv
  • Contact
  • Search
Publication

Application of Work Zone Road User Costs to Determine Schedule-Related Incentives and Disincentives: Conceptual Framework

Author/Presenter: Sadasivam, Suri; Mallela, Jagannath
Abstract:

Time-related contract clauses are primarily designed to encourage contractors through incentives and disincentives to complete construction projects on or ahead of schedule. Highway agencies have gained extensive experience with the application of incentives and disincentives. Agencies typically use work zone road user costs (WZRUCs) as an economic and legal basis to establish incentives and disincentives. It is common practice to estimate the value of incentives or disincentives by applying a multiplier or discount factor to a sum of the estimated WZRUCs and other owner costs. There is adequate literature available on how to estimate WZRUCs and establish incentives and disincentives; however, there is little guidance on the selection of discount factors. In addition to reemphasizing the importance of adequately compensating the contractor for accelerating construction through incentive mechanisms, this paper presents a conceptual framework for effective schedule management that incorporates the costs of construction acceleration and more-objectively estimated discount factors. This study proposes a more objective way of estimating discount factors, such as a project economics–related return on investment assessment, the project work zone disruption risk, the WZRUCs, and the owner and contractor construction engineering costs.

Source: Transportation Research Record: Journal of the Transportation Research Board
Volume: 2504
Issue: 1
Publisher: Transportation Research Board
Publication Date: 2015
Full Text URL: Link to URL
Publication Types: Books, Reports, Papers, and Research Articles
Topics: Construction Scheduling; Costs; Disincentives; Incentives; Work Zones

Copyright © 2023 American Road & Transportation Builders Association (ARTBA). The National Work Zone Safety Information Clearinghouse is a project of the ARTBA Transportation Development Foundation. It is operated in cooperation with the U.S. Federal Highway Administration and Texas A&M Transportation Institute. | Copyright Statement · Privacy Policy · Disclaimer