• Skip to primary navigation
  • Skip to main content
Logo

Work Zone Safety Information Clearinghouse

Library of Resources to Improve Roadway Work Zone Safety for All Roadway Users

  • About
  • Newsletter
  • Contact
  • X
  • Facebook
  • LinkedIn
  • Work Zone Data
    • At a Glance
    • National & State Traffic Data
    • Work Zone Traffic Crash Trends and Statistics
    • Worker Fatalities and Injuries at Road Construction Sites
  • Topics of Interest
    • Commercial Motor Vehicle Safety
    • Smart Work Zones
    • Work Zone Safety and MobilityTransportation Management Plans
    • Accommodating Pedestrians
    • Worker Safety and Welfare
    • Project Coordination in Work Zones
  • Training
    • Online Courses
    • FHWA Safety Grant Products
    • Toolboxes
    • Flagger
    • Certification and
      Accreditation
  • Work Zone Devices
  • Laws, Standards & Policies
  • Public Awareness
  • About
  • Events
  • Contact
  • Search
Publication

Estimating Road User Costs as a Basis for Incentive/Disincentive Amounts in Highway Construction Contracts

Author/Presenter: Gillespie, James S.
Abstract:

The Virginia Department of Transportation (VDOT) occasionally includes an incentive/ disincentive for early completion (I/D) in its construction contracts. This report presents the results of a project to identify procedures that would (1) enhance the effectiveness and enforceability of the I/D provision and (2) reduce the staff time and effort necessary to determine the need for an I/D and to calculate an appropriate per-day dollar amount. The researcher first reviewed the relevant literature pertaining to construction contracts and to road user cost calculation, and then evaluated the available user cost methodologies, especially computer software. Next, the researcher surveyed the current use of I/D provisions in Virginia and other states, and described VDOT’s current project development process, with special emphasis on the user cost data that are typically generated during that process. The report makes five conclusions. First, various forms of I/D, though known by a variety of names, are fundamentally similar. Second, use of an incentive rather than a disincentive alone enhances the enforceability of the disincentive clause, though it may increase the final cost of the contract. Third, cost-plus-time bidding enhances the effectiveness of the incentive clause and the enforceability of the disincentive clause. Fourth, the end of the design public hearing is a logical point for VDOT to judge the need for an I/D. Fifth, road user cost savings calculated from the output of the Highway Capacity Software already in common use in VDOT forms a legally sound justification for a per-day dollar I/D amount.

Publisher: Virginia Transportation Research Council
Publication Date: February 1998
Full Text URL: Link to URL
Publication Types: Books, Reports, Papers, and Research Articles
Topics: Contracting; Costs; Disincentives; Incentives

Copyright © 2025 American Road & Transportation Builders Association (ARTBA). The National Work Zone Safety Information Clearinghouse is a project of the ARTBA Transportation Development Foundation. It is operated in cooperation with the U.S. Federal Highway Administration and Texas A&M Transportation Institute. | Copyright Statement · Privacy Policy · Disclaimer